What is the current time frame for each building makeover, how long did the first one take ? And does the next building seem to be going quicker or about the same ?
There is another thread here https://www.disboards.com/threads/pop-century-room-renovations.3573071/page-111 where the renovation discussions are ongoing. Here is a summary of the progress
Bldg 8, 90's, started renovation on 6 March, opened on 8 June (~renovation time 94 days)
Bldg 9, 80's, started renovation early May, scheduled to open 24 July (~renovation time 80 days)
Bldg 7, 80's, started renovation early June, scheduled to open 14 August (~renovation time 70 days)
No other buildings have been started but guestimating building 10 will be next and should be started in the need week or two, with building 6 being 4-6 weeks behind it getting started.
It appears that they are getting faster as they get more familar with what they need to do. I'm guessing that each remaining building will take ~60 days to complete and that they will start a new building every 30-45 days.
Here is my best guestimate on the remaining schedule
bldg 10 : 25 July - 23 Sept
bldg 6 : 5 Sept - 4 Nov
bldg 5 : 17 Oct - 16 Dec
bldg 4 : 28 Nov - 27 Jan
bldg 3 : 9 Jan - 10 March
bldg 1 : 20 Feb - 21 April
bldg 2 : 3 April - 2 June.
Janet, is there anyway to get the renovation information (buildings completed, under renovations, building renovation start date, etc) in one of the empty top posts. As stated above there is an on-going thread discussing the renovation, but having the summary in one place would be SUPER helpful for many.
EDIT : Corrected Building 8 open date.