Pardon typos I'm working off phone. Actually decided five days real vacation meant no computer.
Today was first day we were at resort when they were working. (Windows are covered.) Left DHS .... crowds. Parks are very busy, which we expected.
We are in 50's ... 24+ POP stays and first with pool view .. upgrade. Nice at moment .. because pool is closed.
We walked to building 8. Poor folks staying close it is noisy! Rooms are being emptied fully, walls built above bath, all new wiring, mud etc. they are currently working on ALL FOUR floors of two wings of building. Other wing has guests literally 20 feet from room work. They have gates, rope and signs so you can't get close.
The first floor wing they started on is still not done. Flooring may be in as they were covered in a paper. Did see a wall sconce installed not seen in pictures placed approx where the fridge/coffee station was or to the left. They looked to be rolling other lights in on carts in boxes.
I found a guy in dressier clothes, vest and hard hat - obviously a project manager person and asked questions. He seemed sure but did say, unless they have changed the plan ... cya.
- Will continue to have Accessible Rooms which have their own different plan.
- As far as he knows ALL remaining rooms will be 1 Bed and 1 Murphy.
- He knows of no other table.
- He said the bathroom door is a "barn style" but he also said it will be "telescoping". We talked on about it and only referring to between beds and sink. I know in pictures it looked like some type of a collapse. Didn't talk of bath to shower. I know some think pocket but there is no space for that. Telescoping is likely to be compared to a pocket.
When I asked about table ... he said "While that is the plan for all, (only Murphy table) no furniture has arrived yet so we can't say for sure." When I walked around to the rooms all said were first started I can verify there was no furniture in them.
I don't think we can work on this 20 day schedule right now. The same area that was started 29 days ago appears to still be in the schedule, with no furniture installed per manager and when I looked in they where empty of hard goods.
View attachment 229318